CompTIA PK0-003 dump is the industry leader in information technology, and getting certified by them is a guaranteed way to succeed with IT careers. We help you do exactly that with our high quality CompTIA http://www.passitdump.com/pk0-003.html training materials. CompTIA PK0-003 dump exam training material in PDF format, which is a very common format found in all computers and gadgets. Regardless of whichever computer you have, you just need to download one of the many PDF readers that are available for free.

QUESTION 1
A project manager is entering the list of a project’s activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the following is the project manager building?
A. Gantt chart
B. Work Breakdown Structure
C. Critical PathD. PERT chart
Correct Answer: A
PK0-003
QUESTION 2
The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited in this situation to show the activities’ logical relationship?
A. Gantt
B. ADM
C. CCB
D. CCM
Correct Answer: B

QUESTION 3
Which of the following is the PK0-003 exam MAIN difference between bottom up and top down cost estimation?
A. Bottom up leads to a more accurate cost estimate than top down because it is performed by subject matter experts
B. Top down leads to a more accurate cost estimate because it is performed by upper management with direct access to budget information
C. Bottom up leads to a less accurate cost estimate because it is breaks down the task into smaller subtasks where some tasks may not have a cost
D. Both top down and bottom up are equally accurate estimation of a project’s total cost because they both refer to resources assigned by the project sponsor
Correct Answer: A

QUESTION 4
Which of the following purchasing processes should a project team use to ensure that the work will be done per company specifications, while selecting the overall cheapest provider?
A. RFI
B. RFP
C. RFC
D. RFQ
Correct Answer: B

QUESTION 5
One of the MAIN purposes of a kick-off meeting is to:
A. Assign and review roles and responsibilities to the project team.
B. Allow the project sponsor to introduce the project manager to the team.
C. Review the project definition document and make the appropriate changes.
D. Ensure project team members communicate amongst each others.
Correct Answer: A

QUESTION 6
After the ground breaking at a new construction site, the pile driving operation comes to PK0-003 vce a full stop due to the nature of the terrain. Which of the following is MOST likely to occur?
A. The project communication plan must be updated and a stakeholder meeting must be scheduled.
B. The project manager must manage the new issue as the project schedule could be delayed.
C. The project manager must implement conflict resolution and review the resource requirement.D. The project scope statement must be reviewed and the project manager must prepare a performance report.
Correct Answer: B

QUESTION 7
A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE about this scenario?
A. The new piece of software will most likely expand the scope of the project therefore a new scope statement must be written.
B. The current project must be completed and a new project can be started to implement the additional software.
C. Quality management metrics are affected therefore the project manager should review the quality of the project.
D. Project schedule may be affected and the project manager must follow the change control process.
Correct Answer: D

QUESTION 8
While performing a scheduled PK0-003 walkthrough at a construction site, the customer points out a discrepancy.
Which of the following is the FIRST step that should be taken before submitting a change control form?
A. Consult the project sponsor
B. Identify the change
C. Perform a feasibility study
D. Perform impact analysis
Correct Answer: B

QUESTION 9
A project team member has identified a required change to PK0-003 pdf one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the following should be done NEXT?
A. Implement the change
B. Update the change registry
C. Document the change
D. Perform an impact analysis
Correct Answer: D

QUESTION 10
Additional company employees have been assigned to the project. Which of the following will be affected?
A. The timeline may be positively affected at the expense of the project cost.
B. This change does not affect the triple constraint because the additional employees are already on the company payroll.
C. The quality of the product will improve but it will add more time to the project to train the new employees.
D. Total project cost will be reduced because the project can now be completed sooner.
Correct Answer: A

QUESTION 11
Which of the following is the project manager implementing when they PK0-003 allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
A. CrashingB. Optimizing
C. Controlling
D. Fast tracking
Correct Answer: A

QUESTION 12
The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (Select TWO).
A. Number of work units affected by the bug
B. Percentage of bug types occurring
C. Software bug counts
D. Root cause of bug occurrence
E. Affect of the bug occurrence
Correct Answer: BC

Read more: http://www.passitdump.com/pk0-003.html Latest and most accurate CompTIA PK0-003 dumps exam material and real exam practice questions and answers are written according to the latest real IT exams. All the questions and answers are revised by the skillful experts. 100% success and guarantee to pass CompTIA PK0-003 dump exam quickly and easily at first attempt.